Lyneham Sports Precinct

Stages 1 & 2 | 2010 – 2011

Stage 1 – Stormwater Works | 2010

Cord Civil was awarded the stormwater civil construction works at the Lyneham Sports Precinct in late May 2010.

The scope of works included installing large diameter stormwater pipes, stormwater structures and large box culverts.  The box culverts were then back-filled allowing a large playing surface for sport and recreation.

Scope of works

Works included environmental protection measures, temporary traffic management, earthworks – including cutting and filling of site materials and importation and disposal of materials as required – stormwater and subsoil drainage, sewer and water reticulation -including provision of a non potable water-main – installation of electrical conduits, street lighting and flood lighting, road pavement construction and temporary and permanent traffic control devices.

Construction of playing fields and associated irrigation, landscaping, quality assurance testing and reporting were also required – plus coordination, commissioning and liaison with asset owners.

Lyneham Sports Precinct Stage 2 | 2011

Works under the Stage 2 contract consisted of the supply and management of all labour, plant and materials necessary for the construction of the Lyneham Sports and Recreation Precinct including associated road and civil infrastructure as well as landscaping works.

Important issues that needed to be managed included erosion and sedimentation control, dust mitigation, geo-technical and environmental supervision. All works were required to comply with the requirements specified by the specification, drawings, and contract in general, and to ensure compliance with all relevant standards, regulations and legislation.

Stage 1 | September 2010

Stage 2 | June 2011

Stage 2 | October 2011