Lower Molonglo Water Quality Control Centre Liquid Waste Receival Facility Upgrade
Client | Waternish/Icon Water
Budget | $2M
Scope of works | The scope of works includes but is not limited to the following:
– Construction of Non-potable water slab
– Construction of Bay 3 Drying Beds consisting of bulk earthworks, detailed earthworks, installation of water and drainage systems, gravel hardstand construction and bulk bedding sand placement
– Installation of 2.4m Icon security fence around both slabs
– Construction of five metre deep wet well and cut-over into main trunk sewer line
– Installation of 300mm diameter sewer pipe between non-potable water slab, bay 3 drying beds and wet well
– Installation of multiple precast sewer pits
– Demolition of Coppins Crossing sewer facility